Key takeaways
- Base the bond on documented needs from a current master plan and condition assessment.
- Budget realistically: include soft costs, escalation and contingency, not just construction.
- Engage the community early and keep district communications informational, not advocacy.
- Prop 39 bonds require a project list, a citizens’ oversight committee and annual audits.
- Have governance and delivery structures ready before the measure goes to voters.
Start with the needs, not the number
It is tempting to start with the question, “How much can we pass?” A better starting point is, “What do our schools actually need?” A bond built on a documented needs basis is easier to explain, easier to deliver and easier to defend.
That needs basis usually comes from a current facilities master plan and condition assessment. If your data is more than a few years old, refresh it before you start sizing a measure.
Build a clear project list
California law requires local school bonds approved under Proposition 39 to include a specific list of projects to be funded. That list becomes a commitment to voters, so it needs to be specific enough to be meaningful and flexible enough to be deliverable.
Work with legal counsel on project list language. Priorities should trace back to your master plan so the board can explain why each project is there.
Get the costs right
Underestimating costs is one of the most common, and most damaging, bond mistakes. Construction cost alone is not the project budget. Soft costs, escalation over the life of the program and contingency can add substantially to the total.
If a bond program runs over several years, projects in later phases will cost more than they would today. Build that into the plan up front rather than cutting scope later and explaining the gap to the community.
- Soft costs: design, DSA review, inspection, testing, permits and program management
- Escalation: cost increases between today and the time each project is bid
- Contingency: reserves for design changes and unforeseen conditions
- Interim housing, furniture, equipment and technology
Engage the community early
Community engagement should begin during planning, not a few months before an election. Listening sessions, site tours and surveys help the district understand priorities and surface concerns while there is still time to respond.
Keep it informational. Districts may use public resources to provide accurate, impartial information about facility needs and a proposed measure, but they may not use public funds to advocate for or against a measure. Consult legal counsel on where that line falls, and keep any campaign activity separate and privately funded.
Plan for oversight and accountability
Bonds passed under Proposition 39’s 55% voter threshold come with accountability requirements, including an independent citizens’ oversight committee and annual performance and financial audits. These are not just compliance boxes; they are how a district shows voters their money is being spent as promised.
Think about how you will report progress before the measure passes. Clear, regular reporting builds credibility for this program and for any future one.
Get governance and delivery ready
Passing a bond is the beginning, not the end. The district needs a plan for how the program will be managed: who makes decisions, how scope and budget changes are approved, how projects are sequenced, and how state matching funds will be pursued.
An honest readiness check before the board votes can reveal gaps while there is still time to close them. K12CG helps districts assess bond readiness and build program budgets grounded in realistic costs.
- Defined decision-making roles for the board and staff
- A change-control process for scope and budget
- A phasing plan aligned with bond issuance
- A strategy for leveraging state School Facility Program funds
Official resources
This guide is general information, not legal or financial advice. State requirements change; confirm current rules with OPSC, DSA or CDE.